View
Graphic: Progress
Map – 3/29/04
Notes:
3/29/04 - Weeks
Marine completed the Outer Harbor Section 933 Project early Tuesday morning
and subsequently
mobilized to the Emerald Isle FEMA Project
that should be completed by Thursday, April 1st. Approximately 700,000 cubic
yards of sand (surveyed) was placed along the shorelines of Indian Beach,
Salter Path, and Pine Knoll Shores as part of the Section 933 effort from
the period of February 8th - March 23rd. That’s a volume equivalent
to a block of sand the size of a regulation 120 yard x 60 yard football field
almost 300 foot high! The communities of Indian Beach and Pine Knoll Shores
have also retained Carolina Seacoast to plant sea oats and bitter panicum
at the intersection of the dune/berm to help promote new dune growth. The
actual planting episode will occur sometime in mid May.
Construction
of the three new access/parking areas planned in association with the Section
933 Project
should be begin within the next couple of weeks.
From east to west these areas include; (1) The Sea Isle Plantation west access
with parking located north of Hwy 58, (2) A walkway located between the Ocean
Club and Salter Path Campground with parking located north of Hwy 58, and
(3) An access/parking area located immediately east of the Baptist Children’s
Home oceanfront gazebo. These new areas are in addition to the Trinity Center,
Roosevelt State Park, and Indian Beach access/parking facilities that are
all located within the Project beach. Stroud Engineering has been retained
for the new construction and the work should be completed in time for the
summer season.
3/22/04 - For the past week, the hopper dredge BE Lindholm has been excavating
the remaining pockets of shoal material from the Outer Harbor reach of the
Morehead City Federal Navigation Project. The material has been pumped in
the vicinity of Station 61.8 near Sea Isle Plantation, Indian Beach and at
a new submerged line landing area at Station 65.9, located at the Roosevelt
State Park in Salter Path. Beach nourishment activity is progressing west
from this point towards the Indian Beach 4WD Ramp/Beach Access (see progress
map above). Although the linear distance of beach nourishment was completed
last Monday, Weeks Marine has been nourishing discreet areas that received
less fill during initial construction that transpired in the past several
weeks.
The dredge RN Weeks should be returning to the area from the Carolina/Kure
Beach Renourishment Project early this week to accompany the BE Lindholm
and complete the Section 933 Project by this Thursday (3/25/04). Weeks Marine
will subsequently mobilize to the Emerald Isle FEMA Project that will utilize
approximately 134,000 cubic yards of sand for beach nourishment along a cumulative
stretch of 12,300 feet of beach and dune construction along a 1,000 foot
corridor located just west of the Old Emerald Isle Pier Access. The borrow
site for the project will be the offshore dredged material disposal site
(ODMDS), which is often used by the U.S. Army Corps of Engineers during routine
annual maintenance (dredging) of the Outer Harbor. The work must be completed
by the March 31, 2004 regulatory deadline.
3/15/04 - The BE Lindholm pumped the last grains of sand along the Pine
Knoll Shores corridor of the Section 993 Project this morning. Although this
completes the linear distance of beach encompassing the Section 933 Project,
Weeks Marine intends to remain in the area and continue dredging the harbor
and placing shoal material along certain areas of Indian Beach near the current
submerged line landing (Station 61.8 - see progress map above).
Weeks Marine has also just been awarded the Emerald Isle FEMA Project that
will utilize approximately 134,000 cubic yards of sand for beach nourishment
along a cumulative stretch of 12,300 feet of beach and dune construction
along a 1,000 foot corridor located just west of the Old Emerald Isle Pier
Access. The borrow site for the project will be the offshore dredged material
disposal site (ODMDS), which is often used by the U.S. Army Corps of Engineers
during routine annual maintenance (dredging) of the Outer Harbor. The schedule
is tentative regarding the Section 933 Project, the Emerald Isle FEMA Project,
and the Carolina/Kure Beach renourishment project that Weeks Marine has all
been awarded, but it appears that the work can be completed by the March
31, 2004 regulatory deadline.
3/8/04 -
The Outer Harbor Section 933 Project is approximately 82% complete and
the beach fill will begin
entering Pine Knoll Shores in the early part
of this week. Weeks Marine continued the Section 933 Project this past Sunday
after a day of “down-time” associated with the southwest gale-force
winds experienced on Saturday (March 6th). The hopper dredge RN Weeks is
scheduled to leave the Morehead City Harbor Section 933 Project today for
the Carolina/Kure Beach renourishment project while the hopper dredge BE
Lindholm will remain on-site until the project is completed. The submerged
line landing for the Section 933 Project is currently positioned at Station
61.8 and beach nourishment activities are progressing eastward from this
point. Please see the Progress Map above for a graphic depiction of these
activities.
3/1/04 - The Outer Harbor Section 933 Project is almost three-quarters complete
as the project enters the fourth week of construction. The submerged line
was moved this past Wednesday (2/25/04) to Station 61.8 near Sea Isle Plantation
(west) and beach nourishment has been progressing westward from this point
where the fill will eventually tie in with the nourishment that was previously
constructed before the submerged line was moved. The Progress map above provides
a graphic depiction of these activities. Construction will begin progressing
eastward from Station 61.8 (Sea Isle Plantation) sometime in the early part
of this week.
2/23/04 -
The Outer Harbor Section 933 Project is entering its third week of construction
and Weeks Marine
have completed approximately 7,000 out of
15,600 linear feet of the project. Fortunately, the weather conditions have
been favorable during this two week time period. The discharge pipe is still
located at the western edge of the Summer Winds Condominium complex (Station
69.1 in the figure above) and beach nourishment operations are progressing
towards the east at the time of this update. The submerged line and the location
of the discharge pipe will likely be repositioned some time this week near
the Sea Isle Plantation corridor of eastern Indian Beach. As mentioned in
last week's update, the fill width & volume is being adjusted along the
beach to accommodate for pre-project conditions while providing a continuous,
straight shoreline throughout the project.
2/16/04 - Dredging
of the Outer Harbor and concurrent beach nourishment began February 8th.
The discharge
pipe is located at the western edge of
the Summer Winds Condominium complex (Station 69.1 in the figure above) and
beach nourishment operations have progressed towards Emerald Isle from this
point to the far western limit of the project near the Indian Beach/Emerald
Isle Town Boundary. The beach fill has now begun progressing eastward from
Station 69.1 and will continue to do so for the remainder of the week. Production
has been very positive for the first week of the Project and the fill width & volume
is being adjusted along the beach to accommodate for pre-project conditions
while providing a straight shoreline. Approximately 25% of the linear distance
of the project has been completed.
2/6/04 - The hopper
dredge RN Weeks has arrived and is docked at the Morehead City Port, and
the submerged line is now buoyed and floating in the Harbor
just north of the Fort Macon Coast Guard Station. The hopper dredge BE
Lindholm is in Norfolk and will join the RN Weeks in the next few days.
We hope that dredging will begin on Sunday or Monday after the forecasted
rough seas subside. On the beach, the submerged line will outfall in Indian
Beach at the Summer Winds Condominium complex near Station 69.1, which
is actually situated at the very western edge of Summer Winds (see progress
map above). The pipe and beachfill will progress west towards Emerald Isle,
and then east from this discharge point (Summer Winds - Station 69.1).
1/27/04 - The
two hopper dredges (BE Lindholm and RN Weeks) that are scheduled to be
employed for the Morehead City Outer Harbor Section 933 Project are presently
completing a project in New York and will begin mobilizing to Bogue Banks
once this project has been completed. Considering the distance and weather
involved with this mobilization, it is expected that the dredges should
arrive sometime the first week in February to start the Section 933 Project.
Weeks Marine is seeking to utilize the Iron Steamer Access in Pine Knoll
Shores as a staging area for dredge pipe and heavy equipment.
1/8/04 – The
U.S. Army Corps of Engineers should formally award the dredging contract
to Weeks Marine next week. It is expected that that mobilization of dredging
equipment and the construction start will occur the last week of January.
How to Interpret
the Progress Map
for
Phase I of the Section 933 Project
Phase
I of the Section 933 Project, or the “Outer Harbor Phase” will utilize
approximately 900,000 cubic yards of dredged shoal material obtained from
the outer harbor of the Morehead City Federal Navigation Project for beach
nourishment along a 3.0 mile stretch of shoreline encompassing Indian Beach/Salter
Path and the westernmost 2,500 feet of oceanfront shoreline in Pine Knoll
Shores. The dredging contract has
been awarded to Weeks Marine, Inc.
Sand that is dredged at the
harbor will be obtained using two ocean-certified, self-contained 4,000-cubic
yard capacity hopper dredges (the B.E. Lindholm and R.N. Weeks)
that essentially store dredged sand in the vessel’s “belly” or hopper. Subsequent
to completing a cut and filling the hopper, each dredge will travel and
discharge sand to a buoyed pipeline located offshore that extends to the
pre-construction dry beach. A secondary “Y-valve” discharge pipe is used
to transport material in one direction (east or west), then the other to
complete ~1-2 mile sections. Dredged sand will be bulldozed into general
construction specifications for subsequent grading into final contours,
tilled, and opened for recreational use.
Project engineers use “stations” positioned along the beach to track
nourishment projects and to verify in-place volumes of sand placed on the
beach by dredging contractors. The stations for the Brandt Island Pump-Out/Section
933 Project are provided in the figure above. These station numbers conveniently
correspond to thousands of linear feet along the beach. For instance,
the distance between station “60” and “61” on the graphic above is approximately
1,000 feet. The distance from station “65” to tick mark “70” is approximately
5,000 feet. If you visit the beaches of central Bogue Banks this winter
you may see wood or metal stakes at the base of the dunes that will identify
these station numbers.
The progress map provides a detailed view of the Section 933 reach
to be completed in the winter of 2004 with station numbers and the location
of the buoyed pipeline. The shaded areas in red represent the completed
portions of the project and will be updated on a weekly basis throughout
the construction.