|
||
SECTION
933 PROJECT |
||
|
Archived Phase I Construction Updates (2004)
|
THE MOREHEAD CITY HARBOR SECTION 933 PROJECT WHAT IS THE SECTION 933 PROJECT? View Graphic: Morehead City Federal Navigation Project View Graphic: Outer Harbor If a local sponsor is interested in paying for the additional costs of transporting and placing sediment on the beach rather than dumping the material in least cost offshore disposal sites, then a cost share program can be implemented under the Corps Section 933 Authority. The incremental expenditures associated with this effort that is planned to place sand along the shorelines of Pine Knoll Shores (PKS) and Indian Beach (IB) are cost shared utilizing a 65% Federal - 35% non-Federal ratio. Historically the State has funded 75% of the non-Federal share of such projects and the Section 933 Project includes this same level of funding. The Corps' Base Disposal Plan is a moniker for routine annual maintenance dredging of the outer harbor that includes offshore disposal. The Section 933 Project is simply the term for the cost-sharing effort to place material dredged from the outer harbor on the beaches of PKS and IB (including Salter Path). Because the volume of material available for beach nourishment for any given year is directly linked to the volume of shoal material residing in the channel at the time of dredging maintenance, the Section 933 project has been divided into two phases that corresponds to two maintenance cycles at the harbor. This should ensure there is an adequate amount of sand to stretch along the shorelines of PKS and IB. Phase I of the Section 933 effort was completed in 2004 and as briefly summarized above, utilized dredged shoal material obtained by hopper dredges from the outer harbor for beach nourishment along the shorelines of IB and the westernmost 2,200 feet of PKS (see figure). For 2007, it is envisioned that Phase II of the Section 933 Project will encompass the remaining portion of PKS. It is also worth mentioning that material from Range B, C, and the turning basin, known as the inner harbor, is removed semi-annually utilizing a cutterhead-suction dredge that essentially excavates sediment from the base of the channel and transports the sediment via a buoyed pipeline in a direct, continuous motion. This material is “direct piped” to Brandt Island, an upland disposal site located north of Fort Macon State Park. Every 8-10 years, the cumulative volume of sediment stored in Brandt Island must be removed to provide accommodation space for new dredged material from the inner harbor. The least cost standard to evacuate the material stored in Brandt Island is to pump this material to the beaches of Atlantic Beach (AB) and Fort Macon. The procedure that includes the final removal of material from Brandt Island is commonly referred to as a “pump-out”. Because this represents the least cost option for the Corps, no cost are incurred by the municipalities, County, or State to nourish the beaches of AB and Fort Macon as a result of this process. Three pump-outs have occurred in 1986, 1994, and 2005 with two separate, smaller-scale direct pipe projects that have nourished Fort Macon (1978 and 2002). The geographic extents for each of these beach nourishment events is depicted below (see link for more information regarding “pump-outs”). View Graphic: USACE Beach Disposal Extent Map I
OFTEN SEE THE TERM “CUBIC YARDS” WHEN
DESCRIBING A BEACH NOURISHMENT PROJECT. WHAT EXACTLY IS A CUBIC
YARD AND HOW
DO I GET A MENTAL PICTURE OF THE VOLUME OF SAND THAT WILL BE USED
FOR THE PROJECT? WHAT IS THE VOLUME OF SAND THAT IS INVOLVED WITH THE PROJECT AND
HOW WILL THIS SAND BE DISTRIBUTED ALONG THE BEACH? After evaluating a series of alternatives in 2002, and again in 2003, 2004, and 2005, a locally-preferred plan has been selected to best meet the needs of the Bogue Banks communities. Although the County is technically the non-federal sponsor, PKS and IB have assumed all terms of local agreement for the Project including funding, easement acquisition, access/parking, etc. The locally-preferred plan is presented below. View Graphic: Locally Preferred Plan One of the primary reasons the locally-preferred plan was developed relates to a desired, “uniform berm” design template that is to be applied over the entire Project area. The uniform berm design consists of the construction of a sand berm at an elevation of approximately 7 feet above sea level and a seaward extension at a 1 vertical to 25 horizontal slope. The volume of sand required to achieve this template varies across the Project area based on the existing condition of the beach. This concept is depicted below. View Graphic: Construction Specifications - "uniform berm" A considerable amount of coastal engineering is utilized to develop these berm template designs and accounts for a certain volume of material to be transported offshore, the re-establishment of an offshore sand bar, and other equilibration aspects. During construction, the berm is extended by over 100 feet and is expected to equilibrate to the berm design (see schematic below). Thus, although each community is receiving a different quantity of sand, the added beach width and storm protection seaward of the primary dune should be the same from the Atlantic Beach/PKS to the IB/Emerald Isle town boundary, i.e., different volumes of sand are required to achieve a uniform height and slope throughout the entire project area seaward of the frontal dune. There is no dune construction planned for the Project. View Graphic: Berm Equilibration In determining the sediment volume required to achieve a uniform design template, the Corps subdivided the entire project areas into reaches. There are actually 70 stations positioned along the beach in increasing numerical order westward from Beaufort Inlet to the IB/Emerald Isle town boundary. The stations are spaced approximately 1,000 feet apart from one another and each of these intervals represents a reach, thus there are approximately 38 reaches (approximately 38,000 feet of linear feet total) that encompass the Section 933 Project area, which the Corps based the project design upon. In this manner, the Corps can develop design alternatives and establish a price per reach cost based on the sediment volume required for each reach. I’VE
SEEN A LOT OF DISCUSSION REGARDING SAND QUALITY IN THE PAST
FEW YEARS. WHAT TYPE OF QUALITY
CAN I EXPECT WITH THIS
PROJECT? WILL THE CONSTRUCTION EQUIPMENT, NOISE, AND BEACH NOURISHMENT
PROCESS IN GENERAL CAUSE ANY MAJOR DISRUPTIONS DURING OUR VISIT
TO THE BEACH? WHY
IS THE TERM “SAND MANAGEMENT” ASSOCIATED
WITH THIS PROJECT? HOW DO I ACCESS THE BEACHES THAT ENCOMPASS THE PROJECT AREA AND
BOGUE BANKS IN GENERAL? While the Corps regulations do not account for issues such as the quality of the access (bathroom facilities, handicap ramps, etc.), or the number of parking spaces above the 10 that is required for each access, the local communities have made terrific progress in meeting the access and parking requirements. IB constructed three additional access/parking facilities as part of the Section 933 Phase I effort completed in 2004. From east to west these areas include; (1) The Sea Isle Plantation west access with parking located north of Hwy 58, (2) A walkway located between the Ocean Club and Salter Path Campground with parking located north of Hwy 58, and (3) An access/parking area located immediately east of the Baptist Children’s Home oceanfront gazebo. These new areas are in addition to the Trinity Center, Roosevelt State Park, and IB access/parking facilities that are all located within the Phase I Project beach. PKS is in the process of negotiating and designing new areas of parking and access at the time this webpage was prepared. Please visit the public access link for a comprehensive view of all access and parking areas located along Bogue Banks. WHAT ARE THE COSTS ASSOCIATED WITH THE ENTIRE SECTION 933 EFFORT? Fact Sheet: Phase I (2004) Fact
Sheet: Phase
II (2007) |
|