The
Pine Knoll Shores/Indian Beach (PKS/IB) Joint Restoration effort represents "Phase
I" of the larger-scale Bogue Banks Restoration Project. The entire
project consists of an ~16.8-mile stretch of Bogue Banks extending from
the Atlantic Beach/Pine Knoll Shores town boundary westward, to approximately
one mile east of the present location of Bogue Inlet. The Bogue Banks Restoration
Project is one of the three supplemental projects that have been aimed
to nourish the beach within the 6 to 8 year interim before the construction
phase of the U.S. Army Corps of Engineers Shore Protection Project is initiated.
The project is sponsored by Carteret County in conjunction with the Towns
of PKS, IB, and Emerald Isle (EI). "Phase I" as stated above
represents the PKS/IB Joint Restoration Project (2001-02), "Phase
II" represents the Eastern EI Restoration Project (2003), and "Phase
III" represents the Western EI Restoration Project (2004-05) that
entails the realignment of Bogue Inlet and the use of the shoal material
dredged during this realignment event for beach restoration purposes.
View
Graphic: Bogue Banks Restoration Project
(A)
Funding
Both
PKS and IB passed bond referendums with special oceanfront and non-oceanfront
tax districts in 2001 to create a fair and equitable method for funding
the project. IB is incurring project costs for IB, the unincorporated town
of Salter Path, and the State-owned portion of the Roosevelt State Park.
The tax rate for the oceanfront and non-oceanfront tax districts in IB
are 0.45 and 0.03 cents per $100 valuation, respectively. IB also levied
a similar tax for Salter Path at 0.43 and 0.03 cents per $100 valuation
for oceanfront and non-oceanfront districts, respectively. PKS levied a
tax of 0.40 and 0.04 cents per $100 valuation, respectively. The entire
cost of the project is $12,585,000.36 with PKS, IB, and the State contributing
$7,549,999.38, $4,135,000.98, and $900,000 respectively. The State has
appropriated $900,000 to defray the cost of nourishment at the Roosevelt
State Park, located within the unincorporated town of Salter Path. Coastal Science & Engineering (CSE)
prepared the Environmental Impact Statement, Environmental Assessment,
Biological Assessment, and construction documents for the project (CSE
2001 & 2002). The dredging contract was awarded to Great Lakes Dredge
and Dock Company (GLDD).
(B)
Project Background
The
PKS/IB Joint Restoration Project can be conceptualized as a 39,202 foot
long project that tapers at the "0" foot mark at the AB/PKS boundary
and the "39,202" footmark at the IB/EI boundary. Sand sources
for the project were delineated in three borrow sites denoted as A, B1,
and B2 on the figure provided below. The project construction and post-project
activities were conducted in accordance with protocols and stipulations
provided in N.C. State Permit Number 124-01 issued by the N.C. Division
of Coastal Management, and Permit Number 200000362 issued by the U.S. Army
Corps of Engineers.
View
Graphic: PKS/IB Joint Restoration Project
Specifications
for the engineered beach were developed using a volumetric analysis (profile
volume method) that was supplemented with historical erosion rate data.
111 transects at ~1,000-foot intervals were established along the entire
length of Bogue Banks in 1999 to assess pre-project beach conditions. At
each transect, the profile geometry was determined by surveying the grade
of the beach from the toe of the dune to the depth of closure estimated
at -12 feet NGVD. The depth of closure in this case was considered as the
depth beyond which there is active motion of the seafloor for only 12 hours
per year (CERC, 1984). Precise volumes were calculated by interpolating
elevation boundaries for each cell and converting the distances and elevational
differences to volumetric quantities. The profile volume method establishes
site-specific criteria whereby volume deficits can be determined against
a designed profile volume that accounts for the overall deficit and incorporates
an additional beachfill volume to increase project longevity (Kana, 1993;
Kana and Mohan, 1998).
View
Graphic: Monitoring Map Insert
AB
was determined as the healthiest portion of beach along Bogue Banks with
the most sand volume along its profiles. AB was most recently nourished
in 1994 as part of the Brandt Island beach disposal event that occurs every
8 to 10 years. Approximately 4.6 million cubic yards (mcy) were pumped
onto the shores of Fort Macon and AB during this event. Development in
AB sustained almost no damage as a result of the tropical storms/hurricanes
that impacted Bogue Banks from 1996-1999. In contrast, approximately $10
million of damage was reported for oceanfront structures in PKS, IB, and
EI (Kana et. al, 2002). Based on this information and additional profile
analysis, CSE determined that 175 cubic yards (cy) per linear feet was
a threshold minimum profile volume. Once this minimum profile volume was
established, volume deficits were established for PKS and IB. The minimum
deficit was augmented by an additional sand volume to increase project
longevity based on erosion rates and final costs for cy of sand. The additional
sand volume was estimated to account for ten years of historical erosion
rates. Thus, the volume of sand placed on the beach for the project was
engineered to provide adequate protection for ~10-year return period events.
This analytical process is detailed in the Executive Summary - Shoreline
Assessment and Preliminary Beach Restoration Plan and the Environmental
Assessment (CSE, 1999 and 2001)
Based
on the profile analysis and bid prices, 770,233 cy of sand were to placed
along the 13,727 foot (ft) stretch of shoreline encompassing IB, Salter
Path, and the Roosevelt State Park, for an average of 65 cy/linear ft in
the non-tapered portions of the project beach. 1,402,983 cy were to be
placed along the shorelines of PKS (an average of approximately 55 cy/linear
foot). Precise volumes per construction transects (design templates) are
included in the construction details and were measured separately by GLDD
and CSE for payment verification. Sand was dredged from the borrow sites
areas using two ocean-certified, self-contained hopper dredges (Manhattan
Island and Sugar Island). Subsequent to completing a cut, each dredge traveled
and discharged sand to a buoyed pipeline with a floating booster that extended
to the pre-construction dry beach. A secondary "Y-valve" discharge
pipe was used to transport sand eastward, then westward to complete each
~1-2 mile section. Dredged sand was bulldozed into general construction
specifications for subsequent grading into final contours and opened for
recreational use. In general, the project was to be constructed from east
to west.
View
Graphic: Discharge
(C) Construction History
During
the initial phases of the project, GLDD were encountering up to 100 tires
a day during sand intaking activities (8,582 total). These tires were derived
from a broken artificial reef complex constructed by the N.C. Division
of Marine Fisheries (AR-342) comprised of 42,000 to 85,000 tires lashed
together with chains. The tires and chains were impeding the flow of sediment
into the dredges, causing a significant amount of downtime. The N.C. Division
of Marine Fisheries collected the tires from the dredges, and a scallop
trawler was subcontracted to sweep the borrow areas for remaining tires
to the most practical extent possible. Because the tires were buried beneath
a thin veneer of sand and are intermittently disbursed in the borrow sites,
there were no indication of tires during coring, magnetometer, or side-scan
sonar study phases of the project. The original dredging construction volumes
were altered to compensate for the tire takings and different areas of
the borrow sites were avoided.
Four
turtles (2 Kemp's Ridley and 2 Loggerheads) were taken during the uploading
of cuts 52 and 53 on December 15, 2001. Per conditions of the operating
permit, dredging operations were discontinued until a Biological Assessment
modification was submitted by CSE and reviewed by U.S. Army Corps of Engineers
and National Marine Fisheries Service. It was apparent that no dredging
operation protocols were breached, nor were there indications that the
takings could have been avoided by the methodology specified in the original
Biological Assessment. Higher than normal water temperatures in the area
were considered the primary cause of turtle occurrences. The project was
permitted to continue with the approved Biological Assessment modifications
on December 21, 2001.
The
unexpected delays combined with mechanical breakdowns near the beginning
of the year (2002) resulted in a few project modifications. A request to
extend the dredging window to April 30, 2002 was granted to permit more
time for beachfill construction activities. Also, permission was granted
to dredge material unconditionally from borrow areas B1 and B2. If borrow
area "A" was to be used, then the 2 to 1 "B" to "A" ratio
should have been applied in accordance with the Environmental Impact Statement.
In terms of construction modifications, a 16% reduction in the total volume
of sand for the entire project was scheduled to compensate for delays and
the overall decrease in production rates resulting from continued tire
takings. The total reduction was 350,000 cy, or a reduction from 2.17 to
1.82 mcy for the entire project (1.18 mcy for PKS, 645,871 cy for IB).
With
the exception of the initial fill areas of PKS, there were project-wide
reductions. To achieve the 1.18-mcy apportionment of sand dedicated to
PKS, the remaining beach fill for PKS was to be 40.5 cy/foot. This accounted
for the volume of sand in the initial "full" cy/foot profile
dimensions that were constructed toward the eastern shoreline of PKS that
is subtracted from the volume of sand required for the remaining stretch
of PKS shoreline. Conversely, the equation for IB was less complex as construction
for this reach did not begin at this point. To achieve the 645,871-cy apportionment
of sand dedicated to IB, the remaining beach fill was to be 54.4 cy/foot,
or a straight 16% reduction from the initial volume. The town boundary
lines were also altered for payment purposes from the 25,875 ft mark to
the 25,475 ft mark. From mid-January to early March, dredging productivity
was it its highest for the project, averaging almost 19,000 cy/day. Permission
was also granted to use Borrow Site A, unconditionally. However, mechanical
problems ensued causing the mobilization of a third dredge (Dodge Island)
to the site in order to complete the project by the April 30th deadline.
The third dredge was on site for a total of 14 production days.
View
Graphic: Dredge Project
The
construction phase of the project was terminated abruptly per permit conditions
and the National Marine Fisheries' Regional Biological Opinion for sea
turtles on April 11th when the fifth turtle (7th Kemp Ridley turtle for
the southeastern seaboard) was taken for the project aboard the Sugar Island.
This left a series of "gaps" in the project, extending from the
foot marks 37,600 to 39,202 (IB), 36,100 to 37,500 (IB), and 31,600 to
33,900 (Salter Path). The Salter Path region that was not completed lies
entirely within the State-owned area of the Roosevelt State Park.
(D)
Final Construction Summary
Work
stoppages associated with turtle takings, tire takings, and mechanical
difficulties resulted in less beachfill than prescribed in the original
contract. For IB, this resulted in a 41% reduction from 770,233 cy (contract)
to 456,994 cy (actual). For PKS, this resulted in a 9% reduction from 1,402,983
cy (contract) to 1,276,586 cy (actual). In terms of linear feet, 3,502
ft were not constructed in IB. Precise beachfill volumes have been documented
by CSE's final post-project surveying activities. The "gaps" in
the project, most notably in the Roosevelt State Park and easternmost IB
area, have equilibrated significantly to the position of the expanded,
project beach berm. Baseline and subsequent high-resolution beach surveying
has provided precise measurements to this effect. Per conditions of the
working permits, tilling was completed for the entire project beach. Subsequent
compaction analysis indicates that the beaches of IB and PKS were -23%
and +11% compacted than pre-project beach conditions, respectively (CSE,
2002).
References
CERC,
1984. Shore Protection Manual. 4th Edition, U.S. Army Corps of Engineers,
Coastal Engineering Research Center, Ft. Belvoir, Virginia, U.S. Governmental
Printing Office, Washington, D.C., 2 vols.
Coastal
Science & Engineering, 1999. Executive Summary - Shoreline Assessment
and Preliminary Beach Restoration Plan, Bogue Banks, North Carolina. Columbia,
S.C.
Coastal
Science & Engineering, 2000. Technical Proposal, Coastal
Engineering
Services for a Beach Nourishment Project, Town of Indian Beach, North Carolina.
Columbia, S.C.
Coastal
Science & Engineering, 2001. Environmental Impact Statement - Bogue
Banks Beach Restoration Plan. Columbia, S.C.
Coastal
Science & Engineering, 2001. Environmental Assessment - Bogue Banks
Beach Restoration Plan. Columbia, S.C.
Coastal
Science & Engineering, 2001. Supplement to Bogue Banks Beach Restoration
Plan Final Environmental Impact Statement. Columbia, S.C.
Coastal
Science & Engineering, 2001. Biological Assessment - Bogue Banks Beach
Nourishment Project, Carteret County, North Carolina. Columbia, S.C.
Coastal
Science & Engineering, 2002. Beach Fill Compaction, Spring 2002 - Bogue
Banks Beach Nourishment Project. Columbia, S.C.
Kana,
T.W., 1993. The Profile Volume Approach to Beach Renourishment. In Stauble,
D.K. and Kraus (eds.), Beach Nourishment Engineering and Management Considerations,
Association of Civil Engineers, New York, NY, p. 176-190.
Kana,
T.W. and Mohan, R.K., 1998. Analysis of Nourished Profile Stability Following
the Fifth Hunting Island (SC) Beach Nourishment Project. Coastal Engineering,
v. 33, p. 117-136.
Kana,
T.W., White, T.E., Forman, J.W., and McKee, P.A., 2002. Shoreline Erosion
Along Bogue Banks, North Carolina. Proceedings from Solutions to Coastal
Disasters Conference, Association of Civil Engineers, San Diego, CA., Feb.
25-27, 2002.