The eastern EI Restoration
Project is actually part of a larger project often referred to as the Bogue
Banks Restoration Project. The entire Project consists of an ~16.8-mile
stretch of Bogue Banks extending from the AB/PKS town boundary westward,
to approximately one mile east of the present location of Bogue Inlet.
The Bogue Banks Restoration Project is one of the three supplemental projects
that have been aimed to nourish the beach within the 6 to 8 year interim
before the construction phase of the USACE Shore Protection Project is
initiated. The project is sponsored by Carteret County in conjunction with
the Towns of PKS, IB, and EI. "Phase I" was constructed in 2001-02
as the Pine Knoll Shores/Indian Beach (PKS/IB) Restoration Project, "Phase
II" represents the Eastern EI Restoration Project (2002-03), and "Phase
III" represents the Western EI Restoration Project (~2004-05) that
may entail the realignment of Bogue Inlet and the use of the shoal material
dredged during this realignment event for beach restoration purposes.
View Graphic: Bogue
Banks Restoration Project
(A) Funding
EI passed a bond referendum
in 2002 with special oceanfront and non-oceanfront tax districts to fund
both Phase II and III of the Project. The tax rate for the oceanfront (Primary
Benefit) and non-oceanfront (Secondary Benefit) tax districts are 0.48
and 0.03 cents per $100 valuation, respectively, that equates to an annual
tax bill of $1,630 (Primary Benefit District) and $53 (Secondary Benefit
District). Proceeds from the County's occupancy tax are also being used
to defray project costs. The cost of Phase II and III, not including interest
payments, is $17,000,000. The cost of Phase II was $11,711,630 and included
expenditures for dune plantings, sand fence installation, mitigative measures,
construction, and oversight. Coastal Science & Engineering (CSE) prepared
the Environmental Impact Statement, Environmental Assessment, Biological
Assessment, and construction documents for the project (CSE 2001 and 2002).
The dredging contract was awarded to Weeks Marine, Inc.
(B) Project Background
Phase II can be conceptualized
as 31,111 foot (5.9 mile) long project that essentially extends near the
old IB Pier (just east of the IB/EI town boundary) at station 382+43 (or
footmark 38,243), westward to Pinta Drive, located in the Columbus Square
subdivision at station 693+54 (or footmark 69,354). Sand sources for the
project were delineated in two (borrow sites B2 and A) of the three borrow
sites (A, B1, and B2) depicted in the figure above. The project construction
and post-project activities were conducted in accordance with original
and subsequent modifications to the protocols and stipulations provided
in N.C. State Permit Number 124-01 issued by the N.C. Division of Coastal
Management, and Permit Number 200000362 issued by the U.S. Army Corps of
Engineers.
View Graphic: Phase
II Map
Specifications for the
engineered beach were developed using a volumetric analysis (profile volume
method) that was supplemented with historical erosion rate data. 111 transects
at ~1,000-foot intervals were established along the entire length of Bogue
Banks in 1999 to assess pre-project beach conditions (Fig. 4). At each
transect, the profile geometry was determined by surveying the grade of
the beach from the toe of the dune to the depth of closure estimated at
-12 feet NGVD (National Geodetic Vertical Datum-1929). The depth of closure
in this case was considered as the depth beyond which there is active motion
of the seafloor for only 12 hours per year (CERC, 1984). Precise volumes
were calculated by interpolating elevation boundaries for each cell and
converting the distances and elevational differences to volumetric quantities.
The profile volume method establishes site-specific criteria whereby volume
deficits can be determined against a designed profile volume that accounts
for the overall deficit and incorporates an additional beachfill volume
to increase project longevity (Kana, 1993; Kana and Mohan, 1998).
View Graphic: Transect
Map Insert
AB was determined as
the healthiest portion of beach along Bogue Banks with the most sand volume
along its profiles. AB was most recently nourished in 1994 as part of the
Brandt Island beach disposal event that occurs every 8 to 10 years. Approximately
4.6 million cubic yards (mcy) were pumped onto the shores of Fort Macon
and AB during this event. Development in AB sustained almost no damage
as a result of the tropical storms/hurricanes that impacted Bogue Banks
from 1996-1999. In contrast, approximately $10 million of damage was reported
for oceanfront structures in PKS, IB, and EI (Kana et. al, 2002). Based
on this information and additional profile analysis, CSE determined that
175 cubic yards (cy) per linear feet was a threshold minimum profile volume.
Once this minimum profile volume was established, volume deficits were
established for PKS, IB, and EI. The minimum deficit was augmented by an
additional sand volume to increase project longevity based on erosion rates
and final costs for cy of sand. The additional sand volume was estimated
to account for ten years of historical erosion rates. Thus, the volume
of sand placed on the beach for the project was engineered to provide adequate
protection for ~10-year return period events. This analytical process is
detailed in the Executive Summary - Shoreline Assessment and Preliminary
Beach Restoration Plan and the Environmental Assessment (CSE, 1999 and
2001).
Based on the profile
analysis and bid prices, 1,810,000 cy of sand were to be placed along the
5.9 mile stretch of shoreline in eastern EI. The profile volume method
described above was utilized to delineate three distinct subcomponents
of the beach where the designed volume of the non-tapered beachfill varied.
The eastern, most critically eroded portion of Phase II that extends for
almost 12,300 feet from the IB/EI town boundary westward was to receive
approximately 83 cubic yards per linear foot (cy/ft). The middle zone encompassing
almost 4,000 linear feet was scheduled to receive approximately 58 cy/ft,
and a westernmost zone encompassing almost 12,900 linear feet was to receive
approximately 35 cy/ft. Discontinuous dune construction was also proposed
for the Project based upon pre-condition beach conditions for a cumulative
stretch of approximately 8,400 feet. Precise volumes per construction transects
(design templates) were included in the construction details prepared for
the Project and were to be surveyed separately by Weeks Marine and CSE
for payment verification. Dredged sand would be bulldozed into general
construction specifications for subsequent grading into final contours
and opened for recreational use. Completed sections were also scheduled
to adjust to natural conditions before the upper reaches of the beach and
newly constructed dunes were stabilized with sand fencing and/or dune plantings.
View Graphic: Cross-Section
Graphic
Sand was to be dredged
utilizing both hopper and cutterhead-suction dredging techniques. While
the working permits did not stipulate dredging equipment specifications,
EI pursued a maximum 6-foot cut within three subareas in borrow site B2
to facilitate the use of a cutterhead-suction dredge. Borrow site A was
limited to a maximum cut of 3 feet which for the most part, constrains
excavation alternatives to hopper dredging which is more productive at
this depth. The 6-foot cut and the anticipated use of a cutterhead-suction
dredge were sought in the interim between the construction of Phase I and
II in hopes of; (1) diminishing the potential of turtle takings, and (2)
increasing production rates that were experienced using hopper dredges
for Phase I construction, which were perceived as "slow". Both
delivery methods employ a buoyed pipeline with secondary "Y-valve" discharge
pipes situated on the beach to transport material in one direction (east
or west), then the other to complete ~1-2 mile sections. The cutterhead-suction
dredge transports material directly to the beach via the buoyed pipeline.
Conversely, hopper dredges utilize vacuum dragheads that collect sediments
and temporarily stores borrow material in its hopper. Subsequent to completing
a cut, the full hopper dredge will travel and affix to a bell joint end
of the buoyed pipeline and propel the material to the beach.
View
Graphic: Discharge
The Federal permit modifications
obtained by EI also established sediment composition thresholds for the
3 or 4-foot and 6-foot cuts. A representative sediment sample was obtained
during each day of operation along each newly constructed reach. Two samples
were obtained per day if both cutterhead-suction and hopper dredging activities
were being conducted along different reaches of the Project. Each daily
sample was a composite of samples taken every 50 feet along a single shore
normal transect from the toe of the dune to the berm crest. The target
calcium carbonate percentage for material placed on the beach utilizing
a cutterhead-suction or hopper dredge was 42 or 35 percent, respectively.
There were no targets established for sediment texture (size, sorting,
etc.).
(C) Construction History
Beach construction was
initiated on January 13, 2003 when the cutterhead-suction dredge RS Weeks
began excavating material from subarea B1 in borrow site B2. However, productivity
remained below expectations (10,260 cy in-place/operation day through February
5, 2003) and it became apparent that additional equipment would need to
be mobilized to complete the Project in the environmental window delineated
in the working permits. Weeks Marine mobilized the hopper dredges RN Weeks
and the BE Lindholm on February 5 and March 6, 2003, respectively. With
the exception of a few trial cuts in borrow site B2 (4-foot maximum cut),
authorized hopper dredge lanes were confined to borrow site A (3-foot maximum
cut). Dredging productivity was at its highest for the Project from mid-
to late-March, averaging approximately 50,000 cy in-place/operation day
cumulatively for all three dredges.
The initial engineering
criteria for dune construction was devised to insure the presence of a
+15-18 feet NGVD dune along the entire Phase II Project area. Consistent
with this approach, dune construction was not planned for areas where dunes
located seaward of individual structures possessed a +15-18 feet NGVD maximum
dune height. Locations below the +15 feet NGVD dune height threshold did
receive a newly constructed dune at a +18 feet NGVD maximum height. Based
on this criteria, dune construction was limited to the easternmost 3 miles
of Phase II. This approach became problematic as the newly constructed
dunes were placed seaward of adjacent existing dunes, providing for a discontinuous
and irregular shore parallel dune system. Based on field reconnaissance
and discussions with citizens, project engineers, and the dredging subcontractor;
it was determined to distribute the newly constructed dune system along
the entire Project reach extending from 10th Street to the old EI Pier
(stations 440+43 to 532+18). The new construction methodology to achieve
the continuous dune profile from 21st Street towards the old EI Pier (stations
501+00 to 532+18) included a 10-foot wide dune crest at +15 feet NGVD,
with a 1 horizontal to 3 vertical slope. Re-grading and shaving the dunes
previously constructed at +18 feet NGVD was completed in the oceanfront
compartment located from the 10th to 21st Street reach (stations 440+43
to 501+00) to fill in the construction gaps in this area.
The Town of EI received
a Notice of Violation from the N.C. Division of Coastal Management during
construction of Phase II dated March 19, 2003 for placing incompatible
sediment on beach in the area of 15th - 21st Streets (stations 468+00 to
501+00). A zone of calcium carbonate sand (shells and limestone fragments)
was encountered by the cutterhead-suction dredge RS Weeks that was the
basis of the violation. The calcium carbonate percentage was over the Project
target of 42% and ranged as high as 87%. Sediment quality monitoring was
being performed during the delivery of this material and the RS Weeks was
instructed to relocate. Also, some of the limestone fragments encountered
in this area were cobble- and boulder-sized. These rocks were manually
removed from the beach per instructions from the U.S. Army Corps of Engineers
in a correspondence that was also dated March 19th. A series of mitigative
and restoration measures have been subsequently established for the area
that predicated the Notice of Violation. These measures are described in
a correspondence prepared by CSE on behalf of EI dated May 5, 2003 and
include such provisions as additional compaction monitoring, the establishment
of an additional beach biological sampling station, sediment sampling,
and continued retrieval and disposal of rocks.
(D) Final Construction
Summary
A total of 1,867,726
cy was delivered to the Phase II Project area by cutterhead-suction and
hopper dredges from January 13 - March 27, 2002. The volume of sediment
delivered by the cutterhead-suction dredge and hopper dredges were 877,831
and 989,895 cy, respectively (1,867,726 cy total). The geographic extents
of the fill per placement method is depicted in the graphic below. Based
on these data, hopper dredging provided approximately 20,632 linear foot
of the fill or 66% of Phase II, while the cutterhead suction dredge RS
Weeks provided approximately 10,479 linear foot of fill or 34% of the total
Project. Other key construction facts and a summary of sediment quality
data for Phase II is included in the following table.
View Graphic: Dredge
Production
View Table: Fact
Sheet
References
CERC, 1984. Shore Protection Manual. 4th Edition, U.S. Army Corps of Engineers,
Coastal Engineering Research Center, Ft. Belvoir, Virginia, U.S. Governmental
Printing Office, Washington, D.C., 2 vols.
Coastal
Science & Engineering,
1999. Executive Summary - Shoreline Assessment and Preliminary Beach Restoration
Plan, Bogue Banks, North Carolina. Columbia, S.C.
Coastal Science & Engineering, 2000. Technical Proposal,
Coastal Engineering Services for a Beach Nourishment Project,
Town of Indian Beach, North Carolina.
Columbia, S.C.
Coastal Science & Engineering, 2001. Environmental
Impact Statement - Bogue Banks Beach Restoration Plan.
Columbia, S.C.
Coastal Science & Engineering, 2001. Environmental
Assessment - Bogue Banks Beach Restoration Plan. Columbia,
S.C.
Coastal Science & Engineering, 2001. Supplement to
Bogue Banks Beach Restoration Plan Final Environmental
Impact Statement. Columbia, S.C.
Coastal Science & Engineering, 2001. Biological Assessment
- Bogue Banks Beach Nourishment Project, Carteret County,
North Carolina. Columbia, S.C.
Kana, T.W., 1993. The Profile Volume Approach to Beach Renourishment. In Stauble,
D.K. and Kraus (eds.), Beach Nourishment Engineering and Management Considerations,
Association of Civil Engineers, New York, NY, p. 176-190.
Kana, T.W. and Mohan, R.K., 1998. Analysis of Nourished Profile Stability Following
the Fifth Hunting Island (SC) Beach Nourishment Project. Coastal Engineering,
v. 33, p. 117-136.
Kana, T.W., White, T.E., Forman, J.W., and McKee, P.A., 2002. Shoreline Erosion
Along Bogue Banks, North Carolina. Proceedings from Solutions to Coastal Disasters
Conference, Association of Civil Engineers, San Diego, CA., Feb. 25-27, 2002.